Construction of the Buildings is 63% Complete
04/19/22 – On the outside, siding and brickwork is currently in progress. On the inside, finishes are starting to be installed, starting on the upper floors and working downwards. Carpeting and plumbing fixtures are being installed on the fourth floor, flooring and cabinetry are being installed on the third floor, and sheetrock and painting are going in on the first two floors. We are on track for completion in early fall.